News Release from: Aker Kvaerner Oil and Gas | Subject: Moomba Gas Plant
Edited by the Processingtalk Editorial Team on 02 December 2004

Rebuild of Santos fire damaged plant
completed

Request your FREE weekly copy of the Processingtalk email newsletter. News about Oil, Gas, Petrochemical Industry News and more every issue. Click here for details.

O and G Solutions, a JV between Aker Kvaerner Australia and United KG has worked with Santos to successfully complete the fast-track rebuild of the damaged Moomba Gas Plant in central Australia

O and G Solutions, a joint venture between Aker Kvaerner Australia Pty Ltd and United KG Pty Ltd has worked with Santos to successfully complete the fast-track rebuild of the damaged Moomba Gas Plant in central Australia Mr Tony Field, Santos Moomba LRP Project Manager said, "That the commissioning went as smoothly as it did is testament to the quality of the works carried out and the professionalism of the alliance workforce

That this project was achieved without a single lost time injury in over 260,000 site man-hours worked is a fantastic effort, and demonstrates the safety culture pervading this alliance group".

Mr Steve Sandler, Chairman of the Executive Committee of O and G Solutions said, "The successful completion of the LRP Rebuild project, which performed well against all project measures, confirms Aker Kvaerner's importance as an alliance partner to Santos".

O and G Solutions has the engineering, procurement and construction (EPC) contract with Santos.

The joint venture responded immediately following the incident in a section of the liquids recovery plant last January to assist in the restoration of Santos' oil and gas production capabilities.

In June, 70 per cent liquids recovery was achieved after the successful reinstatement of process Train A.

The EPC Alliance personnel worked to establish a limited processing capability, enabling Santos to meet its supply commitments.

The focus then moved quickly to the rebuild effort, through well organised engineering, procurement and construction efforts the assessment, demolition and rebuilding of the fire affected areas was completed with excellence in safety and with high quality.

With both process Train-A commissioned in June and Train-B commissioned late August, the Moomba plant is again operating in full liquids recovery mode for the extraction of natural gas liquids such as LPGs and ethane.

Aker Kvaerner Oil and Gas: contact details and other news
Email this article to a colleague
Register for the free Processingtalk email newsletter
Processingtalk Home Page

Search the Pro-Talk network of sites