Product category:
Power supplies and plant cabling
News Release from: AVK|SEG UK | Subject: Standby generators
Edited by the Processingtalk Editorial
Team on 12 March 2008
Rapid supply of standby generators for
ManU
Not only have Manchester United powered their way to the top of the Premiership league, but they also joined up with the generator team from AVK to power their floodlights within the stadium
It was evident to Manchester United that their 'Theatre of Dreams' could become a 'Theatre of Nightmares' if power went off during a match The Manchester United home is Old Trafford, which is often the venue for major European football matches
This article was originally published on Processingtalk on 17 Mar 2008 at 8.00am (UK)
Related stories
Roof mounted generator is vibration shielded
A containerised roof mounted 1000kVA Generator was recently supplied by AVK to a new building for Lewisham Hospital, insulated so as not to keep the patients awake
Robot machine-tending at aerospace manufacturer
Aerospace component manufacturer Centrax has installed an ABB IRB2400L six-axis robot to investigate the feasibility of introducing fully automated machine tending to selected manufacturing processes
Global Quality Culture for Multinational
Product consistency and quality and a mandate to reduce costs spurred container manufacturer Crown Cork and Seal Co to institute quality measures that could be applied for all manufacturing sites
It is simply not possible to be without floodlights and to have to abandon a match because of a utility failure.
TV and the governing football bodies take a dim view of abandoned matches and can impose swingeing financial penalties which hurt the host side very much.
Ian Collins is the main facilities Manager at Manchester United and together with Carl Niland of Hannan Associates they came to AVK with a shopping list filled with demanding conditions.
Firstly a delivery of 2 weeks was required for 2 of the 400 kVA Generators.
Then AVK needed to take a close look at the kind of load the two new generators would be expected to supply in the event of a power outage.
Secondly the new floodlights, being installed at the same time, all come with electronic control equipment.
AVK had to ensure that the generators could cope with the required step loads and that the electronic governors fitted to the generators were of a high enough specification to inhibit any voltage droop or frequency intolerance, as the floodlights would not be able to re-strike quickly and enable play to resume.
Thirdly AVK had to provide 16 changeover switches located throughout Old Trafford which would be timed to bring on various sections of the floodlights.
Everything needed to happen swiftly and the provision of layout drawings, schematics, and detailed information all required instant responses.
Fortunately AVK keep a stock of standby generators so delivery was not a problem.
The actual standby generators at Manchester United Football Club have Scania engines and Newage alternators.
They were supplied with a 75 dBA close-fit canopy arrangement.
AVK then had to prove the system through functional testing which was done with help from the other parties involved in this project.
• AVK|SEG UK: contact details and other news
• Email this article to a colleague
• Register for the free Processingtalk email newsletter
• Processingtalk Home Page


