Roof mounted generator is vibration shielded
A containerised roof mounted 1000kVA Generator was recently supplied by AVK to a new building for Lewisham Hospital, insulated so as not to keep the patients awake
Part of the design objective was to isolate the generator so that any vibration during operation did not penetrate down into the wards below.
This was achieved using layers of sound absorption material within the concrete slab base.
Once the design was verified by the Sound Consultant, the construction took place.
Getting the generator into position was a major task.
Neither of the site cranes were able to lift the generator into position.
Therefore the generator was lifted onto the roof and positioned using bridging steels and skates.
The local fuel tank was fed from the main bulk tank on the site.
However the local tank was designed to hold twice the normal amount of fuel.
AVK designed and constructed a 4 hour rated fire-proof tank which hopefully will allow the patients to sleep peacefully.
To find our more about AVK control systems or generators please contact AVK|SEG direct.
Not what you're looking for? Search the site.
Categories
- Plant Instrumentation (5,478)
- Process Control and Management (2,525)
- Communications and HMI (2,535)
- Process Plant and Equipment (6,164)
- Processing Industry Events and Services (3,198)
- News from specific industry sectors (2,263)
- ENVIRO-Talk - Environment + Pollution (550)
- FLOWtalk - Flow Measurement (753)
- WATER-Talk - Water Industry News (1,211)