Careful extension within operating
pharma plant
Kirk and Blum has turned warehouse space into four cGMP-compliant processing labs in less than four months for a contract pharmaceutical manufacturer, without interruption to manufacturing operations
Kirk and Blum, an operating unit within CECO Environmental, has turned warehouse space into four cGMP-compliant processing labs in less than four months for a contract pharmaceutical manufacturer, without any interruption to the existing manufacturing operations "It takes one to know one" might be a well-worn phrase, but the engineers at a major Midwestern pharmaceutical plant say it's a useful rule to apply when choosing a building contractor for a "hot" project
This article was originally published on Processingtalk on 26 Mar 2007 at 8.00am (UK)
Related stories
Centralised solutions to airborne mist removal
The CECO centralised filter systems reduces pressure drop and energy use, delivers 10-year filter life and 99.5% and greater capture efficiency, and consolidates mist cleaning to a single location
Energy-management and reduction in large plants
A new downloadable CECO Energy Management Team presentation details the cost impact of wasted energy in industrial buildings and processes, and explains how to reduce energy costs in manufacture
As engineers for an award-winning pharmaceutical facility whose work is audited by major drug companies, the FDA and DEA, they have become good judges of other contractors.
So when the plant needed a general contractor to build new processing labs and install a 60-inch tablet coater inside a functioning plant - and do it on a short schedule to meet a customer's product launch - the project went not to a general contractor, but to Kirk and Blum, a sheet metal and mechanical contractor that had earned its stripes on smaller jobs at the site over several years.
The result was a shortening of a projected six-month build time to just under four months, complete with cost-reduction engineering and tricky installations of air handling and dust collecting systems.
Further reading
Xscape to the snow, with ABB low voltage products
Versatility, ease of installation and maintenance and a competitive price were the factors that selected ABB distribution equipment for an electrical services application at the Xscape leisure complex
ABB robots blast away paint build up at Land Rover
ABB, the global power and automation technologies group, has supplied three industrial robots to the Paint Shop at the Land Rover manufacturing facility in Solihull, West Midlands
ADAC Paintbox orders advanced ABB paint robots
ABB, the global power and automation technologies group, has secured a GBP 260,000 order from ADAC Paintbox of Banbury, for two IRB5400 process-arm robots for use on Bentley automotive bumpers
The pharmaceutical plant produces oral solid-dose medications, with a specialisation in controlled-release and taste masking technologies.
The plant serves customers worldwide, producing prescription and some over-the-counter drugs.
"We are the manufacturing arm of major drug companies," explained the director of engineering and maintenance at the plant.
"We must conform to customer manufacturing specifications, as well as the cGMP (Current Good Manufacturing Practice) defined by the FDA and European regulators.
We also have to be quick and competitive.
Time-to-market is everything for our customers.
After years of product development and testing, they want drugs in the market as soon as possible after regulatory approvals.
And with the stiff competition in our industry, we work hard to make our plant the best choice for our customers to manufacture their products".
K and B also brought their own ideas for time and cost reduction, to meet one of the client's customer need for a quick launch of a product, requiring additional processing labs at the plant ready to go by a specific date.
"The start date for the project kept moving back as contract negotiation proceeded, but the start-up date for production was fixed," said the engineering director.
"We received approval for the project just four months before start-up, but assured our management that we could meet the deadline without interruption to current operations, though we still needed to do some value engineering to bring it in on budget.
Our first choice was to act as our own general contractor, but our engineering staff had a full schedule at the time.
Kirk and Blum was the primary sheet metal subcontractor on the job, and had demonstrated in years of past performance that they had the competence to be a general contractor on a project of this size, so to meet the launch date, we delegated the job to K and B".
An A/E firm designed the new facility, but with the tight deadline, "we needed a contractor who could field-engineer on the fly to overcome issues that are inherent in a job like this," he elaborated "K and B had also demonstrated skills in value engineering a job to take out cost and time.
Their project managers offered cost-cutting ideas the engineering firm hadn't thought of, which helped us meet our budget".
The only option at the 100,000-square-foot plant for adding processing labs was to take some space inside the existing warehouse area where the lab rooms could be "grafted" onto the concrete-block wall separating the warehouse and GMP corridor.
The basic plan called for four 20' x 20' processing labs with 12' ceilings and 2' crawl space above for ductwork and HEPA filtration.
Above the lab ceiling is a concrete-over-steel mezzanine floor that holds a 4000-cfm air handling unit for the pan coater installed in one of the labs.
The overall area developed, however, is about 120' x 20' x 30' (LWH).
"We designed for additional labs in the future, and the steel structure and all the utilities are sized appropriately with duct and piping stubbed off, but in place and ready to build out," he added.
To provide a contained work environment, K and B first cocooned the entire work area with plastic, then put it under negative air pressure with monitoring to ensure contaminants could not escape into the warehouse or processing areas, essential to achieve the fast, clean construction needed in a working pharmaceutical plant.
In addition, when the GMP corridor wall had to be penetrated for new doors, it, too, had to be fully isolated from construction dust.
"Keep in mind, we did this inside a functioning pharmaceutical plant and warehouse," explained the engineering director: "Good Manufacturing Practices govern our warehouse operation, too, so dust had to be tightly controlled to protect our people, equipment, and material storage.
We also have to control the construction workers and what they bring on our site.
Personnel control, because of FDA/DEA registration, must be secure and well-coordinated.
Control of contractors on our site is our biggest issue, because it's almost always a contractor that causes a problem for us.
K and B experience with this regimen was helpful on the job site, as well as in enabling them to make an informed project bid".
The scope of work involved structural steel and sheet metal fabrication, concrete removal for installation of footers and drain lines, process piping, process electrical, fire suppression, explosion detection, dry wall, concrete pumping and finishing, painting, and installation of the pan coater.
By using steel studding and epoxy-coated, waterproof dry wall, instead of 12inch-thick concrete block walls, usable floor space is maximised, as is access to electrical, piping and ductwork for future modifications.
In the course of the project, three air handling units were installed, two on the roof and one on the new indoor mezzanine over the pan coater room.
The mezzanine air handling unit weighed 15,600 pounds and was installed in two sections on the mezzanine by clever rigging with just 27'' of height clearance.
A new dust collector for the pan coater also had to be brought indoors in four sections, down a tight hallway, and shoe-horned into a "parking space" between other collectors with just 3/4'' of clearance at some points.
"These are the kind of field problems that stymie most contractors and can't be engineered from an office," said the engineering director: "In one instance, K and B quickly adapted a change we needed in a wall to prevent it from covering up an important floor drain that had been misplaced by the design engineers.
In recent years, K and B has helped us keep our dust collectors indoors for convenience of service by converting a number of bag-type collectors to cartridges.
This helped us in two ways.
We can get more collectors in a tight space, yet still have room for side-access service.
The washable cartridges also increased the air flow capacity of the collectors, which allows us to increase our process throughput, yet keep solvent fumes diluted well below the LEL.
On an earlier project in this same area, K and B field-designed a trombone-shaped section of duct work to fit a small space, giving us the duct length needed to properly space explosion sensors and dampers.
They can look at these tight spots, take measurements, come up with a solution that fits the space, and then give me an engineering drawing in the end".
"Careful staging of the work with trusted subcontractors, plus off-site prefabrication of as much steel and sheet metal as possible, minimised our impact on the site and helped us complete the job without overtime," said Jim Carr, the K and B project manager: "It's a matter of looking down the road for the potholes and working with the subs and owner to keep things on track".
Without this kind of attention, said the plant manager, almost no amount of oversight or complaints would have helped much.
"There was almost no margin for error on this project, and they stayed well within it.
We originally hoped to get just the one lab with the new pan coater in operation by deadline, but we completed all of them on time and budget, including a multipurpose room we had not even planned to finish out".