MCERTS flow certification - The First
Steps

Request your FREE weekly copy of the Processingtalk email newsletter. News about Water News and Legislation and more every issue. Click here for details.

In this article Paul Cherry, a member of the MCERTS Project Steering Committee (PSC) and the first qualified MCERTS inspector, explains how the new system works

In January 2004, the Environment Agency (EA) extended its Monitoring Certification scheme, MCERTS, to cover the self-monitoring of effluent flow Under the new scheme, consent holders (processors who have been granted Consent to Discharge by the EA) must have their sites certified by a qualified MCERTS inspector whose job it is to check that flow structures and instrumentation comply with the relevant legislation

All qualifying sites must be certified by March 2005, so water companies need to get to grips with the new requirements.

However, as admirable as the new MCERTS scheme is, it is only the first step to overall compliance.

The Urban Waste Water Treatment Regulations 1994 and Water Resources Act 1991, contains provision allowing the EA to set specific consent requirements particular for each site, which can go further than requiring data for just the rate of discharge flow and cumulative daily volumes.

Other site process flow diurnals, storm flows and intermittent discharges (storm events) may also need to be monitored and reported on a regular or periodic basis.

Whilst these may not be included in MCERTS, they are still a legal requirement.

In this article Paul Cherry, a member of the MCERTS Project Steering Committee (PSC) and the first qualified MCERTS inspector, explains how the new system works.

At the same time he sounds a note of caution, highlighting that industry should not lose sight of the higher legislation that the scheme can be designed to serve.

He also notes that there could be considerable cost savings in the long term for water companies who plan towards the bigger picture, rather than immediate MCERTS requirements.

MCERTS SELF-MONITORING.

The Environment Agency requires consent holders to install and maintain equipment to measure and record instantaneous and cumulative daily flows at discharges above 250 population equivalent, or have a dry weather flow (DWF) equal to or greater than 50 cubic metres/day.

The total daily volume of effluent reported should be measured with an uncertainty of better than +/-8% and a confidence level of 95%.

Successful effluent flow monitoring depends on operators embodying correctly applied installations, combined with appropriate equipment, calibration, maintenance, quality assurance and data management.

These should be managed within a quality system that can be routinely audited to ensure that performance can be maintained over time.

The MCERTS self-monitoring scheme sets minimum requirements for the following, all of which are to be inspected and verified by the appointed (third party) MCERTS inspector.

Flow structures and devices, eg flumes/weirs/electromagnetic meters.

Monitoring equipment, eg level sensors.

Data gathering and transmission eg analogue to digital.

Associated quality-assurance systems.

The scheme operates as follows.

An MCERTS inspector shall be contracted by the consent holder to provide an independent assessment of each site and the quality assurance system.

The inspector makes a detailed analysis of the flow measurement installation and prepares a report putting forward his or her expert opinion as to whether or not the site meets the MCERTS standard.

Vendor neutral recommendations for remedial work may also be made.

On the basis of the inspectors successful report, the MCERTS Inspection Body issues a certificate for the site in question, valid for five years.

GOING FURTHER THAN MCERTS.

At the moment, MCERTS primarily focuses on DWF in and out of the site.

It does not embrace measurement of storm overflows (intermittent discharges), or settled storm flow figures.

The EA specifies the quality and quantity requirements for discharges including flow.

However, OFWAT has the responsibility to ensure adequate wastewater collection and treatment provision in each area, and with it the authority to require water companies to increase their treatment capacity according to rainfall and population figures.

This is a legal requirement under the Water Industries Act - something that water companies should not lose sight of in the rush to achieve MCERTS certification.

While the EA is taking a one-step-at-a-time approach to enforcing regulations, a few more progressive, leading water companies are saving significant resources by keeping their focus on the wider legislation.

Investing in more intelligent solutions now, which provide total flow and compliance data, not just the immediate MCERTS requirement, puts them ahead of the game.

For example, MCERTS requires that "The location of the flow monitoring installation shall ensure representative measurement of the total volume discharged (Minimum requirements for the Self-Monitoring of Effluent Flow paragraph 3.2.2).

On many sites, the most obvious solution may be flow measurement at the outflow.

However, an inlet measurement, downstream of the storm overflow flume, may also meet the requirement, and by including data logging equipment, a single installation could be set up to provide both total daily volume (to MCERTS) and storm overflow event data.

Although the initial investment would be marginally greater, there would be significant long term savings due to combined legal requirements being achieved at once.

MCERTS says that "The total daily volume of effluent must be measured with a target uncertainty of better than 8% and a confidence level of 95%.

" (Minimum requirements for the Self-Monitoring of Effluent Flow paragraph 3.2.1).

This can sometimes be somewhat misleading as they apply to the entire flow measurement system, not just to the primary flow structure and secondary instrumentation.

For complete legislative compliance, it is the ultimate data recorded at the data archive which must achieve the 8% criteria.

On the majority of sites, data acquisition systems include some sort of telemetry or other data network and acquisition and analysis software, which, by definition, must introduce some error to the final data.

It is therefore essential to check the accuracy of the combined system, including the signalling network and software, to ensure compliance.

CONCLUSION.

The EA describes MCERTS as being there to provide assurance about the reliability of flow measurement data to all stakeholders, and to establish a level playing field in the competitive flow measurement market.

The scheme will do this, and more, not least in helping to raise professional standards in flow auditing.

MCERTS does not replace all previous legislative compliance requirements.

The EAs own pioneering P150 document and Procedure for Flow Measurement of Discharges (Sep 2000) are still the fundamental basis for the interpretation of the Water Resources Act 1991.

The much wider and far reaching obligations for consent holders described in these documents, along with specific site consent conditions, are still enforceable by the EA.

There is a strong business case for a long term, balanced approach to planning and compliance.

For water companies who make this the basis of their business strategy, MCERTS compliance is one complementary component, of a long term plan.

Emerson Process Management - Mobrey Measurement: contact details and other news
Email this article to a colleague
Register for the free Processingtalk email newsletter
Processingtalk Home Page

Search the Pro-Talk network of sites

Visit the Camlab web site